AAC Vertical Wall Panels
Tools required for installation


Step 14
Attach galvanized corrugated nails within vertical
joints one at 2'-0" from the top af wall and one at 2'-0" from the bottom of wall vertically or as required using
a hammer.

Step 15
Align and install remaining panels in accordance
with steps 7 through 14.

Step 16
Install reinforcing steel then pre-wet core and then place
concrete (flowable grout) within vertical
panel joints according to drawings.

Firmly tamp into joints and screed
off excess.

Step 17

As needed, rasp (sand) the topside of the wall to ensure a level and flat surface. With a brush, sweep off dust and loose particles.