AAC Vertical Wall Panels |
|||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||
|
Step 1 Check panel layout of approved AAC shop drawings and deliver panels to jobsite accordingly. |
Step 2 Unload the bundles of panels in a proper manner using approved unloading gear. Protect the panels from rain and water saturation by leaving them on pallets and away from standing water. |
|||||||||||||||||||||||||||||||||||
|
Step 2 (continued)Eliminate excessive handling by storing panels nearest to where they will be installed. |
Step 2 (continued)Protect the panels when traveling on uneven ground. |
|||||||||||||||||||||||||||||||||||
|