AAC Vertical Wall Panels
Installation Process


Step 1
Check panel layout of approved AAC shop
drawings and deliver panels to jobsite accordingly.

Step 2
Unload the bundles of panels in a proper
manner using approved unloading gear.

Protect the panels from rain and water saturation by leaving them on pallets and away from standing water.

Step 2 (continued)
Eliminate excessive handling by storing
panels nearest to where they will be installed.

Step 2 (continued)
Protect the panels when traveling on uneven ground.