Step 1 - Layout wall lines.Lay out wall lines on building slab by control lines. |
Step 2 -Start the leveling bed. At the highest corner of the slab place a full width 1/2" deep sand-cement mortar joint using a masonry trowel (Mortar to be either Ready-Mix or 3:1 Sand: Portland Cement ratio or approved then-bed mortar). Salvage additional mortar. Do not use thin-bed mortar for the leveling bed joint. If moisture and wicking is a problem, add water resistance mixture to sand-cement mortar. |
||||||||||||||||||||||||
|
Step 3 - Set the first corner block.Set the first corner block in the sand -cement mortar and adjust the joint as needed. To achieve the required height, lower or raise the block by tapping down with a rubber mallet or by adding additional mortar beneath. |
|||||||||||||||||||||||||
|
Step 4 - Mix thin-bed mortar.Mix approved AAC thin-bed mortar in a clean mixing container (5-gallon bucket or pail) per manufacturer's directions. The consistency of the mixed thin-bed mortar should be such that it flows easily through the teeth of the notched trowel leaving the shape of the teeth in the mortar bed. Thin-bed mortar droppings should not |
|||||||||||||||||||||||||
|
SafeCrete |
End Page 3 |
||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||