AAC Horizontal Wall Panels |
||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||
|
Point 1 Supporting columns must be plumb, level and within linear building line tolerances. |
Point 2 Protect the panels from rain water saturation by leaving them on pallets and away from standing water. |
Point 3 Set panels with tongue side up and follow specifications and shop drawings for placement of adhesive and joint filler. |
||||||||||||||||||||||||||
|
Point 4 Panel(s) must lay flush against face of column or steel shim plates. |
Point 5 In the event bowing occurs with the AAC panels within a column bay, |
|
||||||||||||||||||||||||||
|
Failure To Adhere To |
||||||||||||||||||||||||||||
|
SafeCrete |