Deliver only an amount of material that can readily be installed.
Unload panels using pallet forks (either forklift, nylon straps, slings or pallet fork on a crane cable). Consult your OSHAA safety manual for "rigging" or other safety considerations.
Storage areas should be accessible to delivery trucks and convenient to material staging areas. If possible, drop-deliver the material right to the material staging areas.
Storage material should always be stored away from other construction activities on a flat-grade area that is not susceptible to standing water, erosion or settling.
In adverse weather conditions, keep the material covered and banded until ready for installation.
|
Special Considerations For
Panel Construction
As with most precast concrete products, the panels should be set directly from the delivery trailer, if permissible.
If the materials cannot be set directly from the delivery trailers, deliver only an amount of material that can be installed readily.
Do not "shake-out" stored materials until they are ready to be installed. Excessive handling may cause damage. Set delivery schedule to match the erection sequence exactly.
Most chipped corners and edges can be repaired. If any reinforcing is visible, contact an authorized AAC representative.
All damage must be repaired using an approved structural-grade AAC patching compound developed specifically for AAC products.
AAC panels that have surface or minor cracks are usable, but contact an authorized AAC representative when cracks continue completely through the panel.
Stored or staged materials should always be set on flat, load-bearing, stable grade on pallets or dunnage.
|