AAC Precast Block Walls |
|||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||
|
Step 3 - Remove waste and clean.If a circular saw or concrete cutter was used to cut the channel, the unwanted material can be removed by snapping it away with a chisel. |
Step 4 - Cut recesses for outlets.Cut a template to the size of the hole or outlet and temporarily secure to the wall. Remove AAC material with a plunge router to the required depth. |
|||||||||||||||||||||||||||||||
|
Step 5 - Install conduit.Install cable, flexible, or rigid conduit in channel and secure with channel clips. Observe local codes for type of conduit, proper attachment and channel depth. |
Step 6 - Install electric boxes.Electrical boxes may be fixed to the wall with course threaded screws. As an option, glue, foam or thin-bed mortar may be used. |
|||||||||||||||||||||||||||||||
|
SafeCrete |
End Page 2 |
|||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||