AAC Precast Floor Panels
Installing Panels


Step 1 - Unload Bundles
Unload bundles of panels in proper manner using approved unloading gear. If panels must be stored, place them in a clean area without standing water that is close to where work will begin.

Step 2 - Layout Bearing Lines
Using a tape measure, layout and chalk the bearing (overlap) lines on top of walls using detail drawings approved for construction. Make sure all bearing, top-of-wall surfaces are level. Rasp or sand down high spots. Fill low spots with shims.

Step 3 - Attach Panel Lifting Gear
Place panels in a flat position with topside up. Attach approved panel lifting gear (slings, forks, or clamps) to the first panel. Be sure to observe manufacturer's proper attachment procedures and safety guidelines.

Step 4 - Place First Panel
The first floor panel is lifted, placed and adjusted into exact alignment along bearing lines. A person is required to steady and guide each end of the panel. Note the edge profiling and mark number of the panel, and install accordingly. Maintain minimum bearing according to drawings.

Bearing pads should be placed on top of wall where the bearing of the floor panel will occure.

 

 